May 2023
The ground floor is for sale with a 10 year lease to Coles. Coles is expected to begin trading in November.
![]() |
263 Normanby Rd, getting ready for Coles May 2023 |
December 2022
April 2022
R.Iconic is a 31 level development comprising ground-floor retail, supermarket and a 5 level podium.
Construction is well underway, utilising HBS (Hickory Building System), a prefabricated and integrated construction solution with no live edge activities making it the safest system for multi-storey construction.
January 2021
Noting the status of this development at the start of 2021. The Oakwood development at 202 - 204 Normanby Rd (left) and the Normanby at 199 - 201 Normanby Rd (right) are clearly visible. The former Dunlop factory is in the foreground.
The development will contain 456 apartments over 37 and 40 storeys.
Architect: Plus Architecture
Builders: Hickory
Landscape: Paul Bungay
R Iconic viewed from Boundary St |
September 2020
Work is underway on site.
R Iconic viewed from Boundary St |
May 2020
R Iconic is 'coming soon'. Refer to R Corporation's website to see what the development will look like.
May 2020 |
March 2020
Work has resumed on site.
Exemplary tree protection on both Normanby Rd and Boundary St.
August 2019
The site is being cleared by Delta.
December 2017
Development permit No. PA170223 was approved by the Minister for Planning - dated 5 December 2017.
VCAT Ref P1604/2017.
September 2017
The Oxford University Press site
R Corporation's proposal for this site includes constructing two towers of 33 and 42 storeys including a five level podium containing ground floor level retail and townhouse dwellings, and apartments and a 147 room residential hotel above.
The Minister for Planning is the decision maker for this site, but the Council's advice is sought.
The Council resolved to advise the Minister that they did not support the application because, amongst other things
Work has resumed on site.
Exemplary tree protection on both Normanby Rd and Boundary St.
August 2019
The site is being cleared by Delta.
![]() |
August 2019 |
December 2017
Development permit No. PA170223 was approved by the Minister for Planning - dated 5 December 2017.
VCAT Ref P1604/2017.
September 2017
The Oxford University Press site
R Corporation's proposal for this site includes constructing two towers of 33 and 42 storeys including a five level podium containing ground floor level retail and townhouse dwellings, and apartments and a 147 room residential hotel above.
The Minister for Planning is the decision maker for this site, but the Council's advice is sought.
The Council resolved to advise the Minister that they did not support the application because, amongst other things
- Tower 1 would overshadow Tower 2
- The communal open space would be overshadowed
- The buildings would overshadow nearby Fennell Reserve between 11.00am and 2pm on September 22
- Visual bulk
- Poor thermal performance
The proposal is headed to VCAT since a decision was not made within the required time frame. There will be a Directions Hearing on 05 or 22 October
(tbc) and a hearing commencing 28 November 2017 for four days.
The full Council report 19 September 2017
8 June 2016
R Corporation bought the Oxford University Press site for $36.35 m.
8 June 2016
R Corporation bought the Oxford University Press site for $36.35 m.
"...The towers will overshadow Fennell Reserve (between Boundary and Ingles St) between 11 and 2 pm at the equinox...." Does this mean overshadowing ~20 March to 23 September every year that is all Winter? https://www.timeanddate.com/calendar/spring-equinox.html
ReplyDeleteHi Steve, I regret that I think that is the case. I will check the VCAT decision. At the time this development was approved, overshadowing controls tailored to Fishermans Bend had not yet been approved. The winter sunlight control is rare to achieve in planning.
ReplyDelete